Who can object?
Any owner in the building, their legal representatives or heirs can object to a risky structure decision. No majority is needed at this stage; a single owner can object. Tenants, however, have no right to object to the decision.
What is the deadline and where do you apply?
The deadline is 15 days from the date the decision is served. If you miss it, you will generally lose the right to object and the decision becomes final. So note down the day you receive the notice.
The objection is made by written petition to the Provincial Directorate of Environment, Urbanisation and Climate Change or to the authorised administration. A technical committee, which includes university and professional chamber representatives, reviews the objection and makes the final technical decision.
What if the objection is rejected?
You can take the technical committee’s decision to the administrative court. The deadline for filing is generally 30 days from service of the decision. But filing a case does not by itself stop eviction and demolition; for that you need to ask the court for a stay of execution.
Our advice: before objecting, get your own independent engineer’s opinion. Have the concrete strength, reinforcement and soil data in the report reviewed. Objections without solid technical grounds rarely succeed and only prolong the process.
We explain the assessment step by step on our risk assessment page.
It is worth remembering that a risk assessment is not a punishment but a warning. If the report says your building could be seriously damaged in an earthquake, it is often wiser to spend that time planning a safe new building than to lose it in an objection. If you are unsure, call us; we will read the report with you and answer your questions in plain language.
This article is for general information only and is not legal or financial advice. Rules and amounts can change; check the current position with the Provincial Directorate, your municipality or your lawyer before you act.